A boat landing under construction in the Penobscot County town of Orrington will be named for Alan Baker, who owned and published the Ellsworth American for 27 years and founded the Mount Desert Islander in Bar Harbor in 2001.
The landing, which will provide recreational and emergency responder access throughout the tidal cycle, is located on the east side of the Penobscot River estuary.
Baker, a longtime resident of Orrington, served in the Maine House of Representatives and was Mainebiz’s first-ever Business Leader of the Year in 2001 when the annual awards program began.
Long time coming
The town acquired the property in 1991 and formed the Orrington Landing Committee in 2020 to investigate and research the feasibility of developing a boat landing on a town-owned, 10-acre lot at the end of McGinn Road off River Road, also known as Route 15.

In 2024, the town received $2.55 million for the project from the Greenfield Environmental Trust Group in Watertown, Mass., which is responsible for disbursing settlement funds paid by Mallinckrodt US LLC to remediate mercury pollution in the Penobscot River estuary from a former chemical manufacturing plant in Orrington.
The facility consists of a 24-foot-wide ramp and upland parking for trucks and trailers and future amenities including picnic areas, hiking trails and a playground.
The project was driven in part by the increasing popularity of recreational boating for Mainers and tourists, the town has said. It’s anticipated the facility will serve more than 50,000 residents between Bangor and Bucksport.

The project team includes Orono construction company Sargent Corp. and Jacobs Solutions in Boston, led by professional engineer Craig Morin.
The project recently secured the last of the state and federal permits and approvals needed.
Removable piles
Work in the intertidal zone must take place during the period between early November and late April, said Keith Bowden, the committee’s chair.
The intertidal zone is the area between high and low tides. The project is complicated by 14-foot tidal variations and winter ice in the river.
“We have to design piles that support the floating docks going up and down,” said Bowden. “Plus we want the piles to be removable so we can pull them out at the end of the boating season.”
Working with South Portland float system maker Custom Float Services, the team is developing a removable pile and dock system.
Once completed, the landing is expected to provide new opportunities for boating, fishing and outdoor recreation. A nearby ramp in South Orrington is too short to be used other than mid- to high tide, and the launch area is narrow and lacks amenities, said Bowden.
The new facility is designed to be fully operational during all tide cycles and to endure sea level rise for the next 50 to 100 years.