Great Falls Construction is involved in southern Maine elementary school projects, with two in the works and a third just finished.
The Gorham-based firm broke ground on a new 111,000-square-foot, $89 million middle school for Cape Elizabeth in October, on a parcel of land off Scott Dyer Road, between the existing middle school and the high school.
The project team is wrapping up ledge removal and foundation work is scheduled to start this week.
The new school will have 25 classrooms, along with rooms for band, chorus and art programs, multiple small collaboration and specialty rooms, a library, cafeteria, gym, dual-sided stage and offices.
Joey Smith, Great Falls’ business development and marketing manager, told Mainebiz the team will demolish most of the current middle school addition that was built in the early 1990s, but protect the original 1934 school building, as the town decides on potential future uses.
“Once the demolition is complete, we’ll construct a new multipurpose athletic field in place of the old middle school building,” Smith said.
R.J. Grondin, based in Gorham, has handled sitework, and the project was designed by Harriman, which is headquartered in Portland.
The Great Falls team will also create a 5,000-square-foot addition and interior renovations to the town’s elementary school, which is connected to the current middle school.
Both school projects are expected to be completed by fall 2028.
Cumberland/North Yarmouth projects
A half-hour north in Cumberland, Great Falls has wrapped up a 6,600-square-foot, four-classroom addition to the Mabel I. Wilson school, topping it off with a new roof.
The school is part of the expanded school campus off of Tuttle Road and currently serves students in grades pre-K through third from Cumberland and North Yarmouth.
Still under construction on the campus is a 76,700-square-foot, $35 million school which will serve students in pre-K through first grade. Great Falls broke ground on the Carolyn F. Small school in June 2025, on a 2.3-acre lot adjacent to the School Administrative District No. 51 campus. It’s expected to have capacity for 550 students in 30 classrooms when completed in June 2027 and will have the ability to be expanded in the future.

“We’re working on getting the building enclosed for the winter so that work on the interior can happen throughout the cold weather,” Smith said. “The roof is nearing completion, along with interior rough-ins, with drywall going up in some areas.”
“These projects for SAD No. 51 are a commitment to the district’s mission of ‘one campus’ where a student can enter pre-K and remain within the same proximity throughout their educational career,” Smith added.
“Great Falls Construction has been engaging with students too, through their ‘Hard Hat Chats’ series where an older student interviews our construction team. The interviews are filmed and shared to spotlight the crew.” Six episodes can be viewed on YouTube.

North Yarmouth-based A.H. Grover Inc. is managing site work on the Small School and Stephen Blatt Architects, based in Portland, is the design team.