Already a Subscriber? Log in
Get Instant Access to This Article
Subscribe to Mainebiz and get immediate access to all of our subscriber-only content and much more.
- Critical Maine business news updated daily.
- Immediate access to all subscriber-only content on our website.
- Bi-weekly print or digital editions of our award-winning publication.
- Special bonus issues like the Mainebiz Book of Lists.
- Exclusive ticket prize draws for our in-person events.
Click here to purchase a paywall bypass link for this article
A South Paris maker of modular construction units said its delivery of projects to the island of Nantucket, Mass., could be a test case for the usefulness of the construction method in logistically tricky locales.
The firm is manufacturing modular housing for a workforce development for Our Island Home, a skilled nursing and elder care facility on Nantucket.
The general contractor is Consigli Construction, which is based in Massachusetts and has a Portland office.
“We're building a two-story building, about 8,000 square feet, out of 12 modules,” said Thatcher Butcher, KBS’s president. “It's designed to a 140-mile-per-hour wind rating with some extra detailing for the coastal environment.”
Production of the project - the company's second for Nantucket - started at the South Paris facility and is due to be delivered soon. The modules will go by truck to the coast and then across on a barge.
In 2024, KBS Builders delivered to Nantucket 14 modular units totaling over 10,000 square feet, assembled into a 20-apartment workforce housing building. “The folks there saw that we understood how to navigate the complexities of work on the island, hit the schedule and the budget,” said Butcher.
Test case
The projects could be test cases for modular construction: Nantucket is challenging because everything gets there by water, said Butcher.
“Every module, every stick of material, every trade,” he said. “So the whole job is about coordination. You're lining up barge weather windows, staging space on the island and crane time, and if one of those slips, the rest slips with it. The island also doesn't have the labor to stick-build a project like this on any reasonable schedule.”
As a test case for modular, “it's not that different from building in rural Maine,” he said. “In both places, you're short on materials and short on labor, and those are exactly the problems modular solves. We’re able to reduce a project like this to a handful of barge trips instead of hundreds, and weeks on site instead of months.”
Other jobs
KBS designs and manufactures modular structures for residential, commercial and mixed-use buildings, working with developers, general contractors, architects, and builders to customize and produce the type of modular structure they’re seeking.
Founded in the early 2000s, KBS is a subsidiary of Old Greenwich, Conn.-based Star Equity Holdings Inc. (Nasdaq: STRR; STRRP). Its main office and factory, spanning 100,000 square feet, are in South Paris; a second factory is a short distance away in Oxford.
Contracts in Maine in recent years include scores of apartment, condominium, townhome and single-family developments.
Earlier this year, KBS was awarded a contract to manufacture 36 modules for the construction of six 2-unit buildings totaling 26,088 square feet as part of a residential assisted living facility in New Hampshire.
In 2025, KBS signed two commercial contracts to manufacture housing units in Maine: 32 modules for the construction of 20 mixed-income housing units in Portland; and 28 modules for the construction of townhouses comprised of 14 housing units in Bowdoinham.
Once the units are built in the factory, they’re shipped to the site, assembled and connected to utilities.
Although the process doesn’t save on upfront costs — labor and materials are just as pricey off-site as on-site — it can save on carrying costs. An apartment building can be ready in months, versus years, lowering development costs and generating rents sooner, Butcher previously told Mainebiz.
The New Hampshire multifamily job is complete and set in place, with the general contractor finishing up site-related work and occupancy of the first units expected later this month.